Stargate Abilene

Crusoe / Lancium (Oracle lease) · Abilene, Texas

Water — consumed, not returned

Taken from the basin450M gal/yr
Evaporated on site52.2M gal
Making the power397M gal
Basin stressHigh
Where the water comes from
Municipal potable supply
Cooling
Closed-loop direct-to-chip liquid
Basis
Modelled from cooling design — WUE 0.09 L/kWh

Air — what the stacks emit

Nitrogen oxides512t/yr
Sulphur dioxide248t/yr
Fine particulates53.6t PM2.5
Health damages$43.6M/yr
Where it burns
ERCOT — Texas + 30% turbines on the site itself
Generation mix
Gas 40 · Wind 24 · Solar 11 · Coal 13 · Nuclear 9
Emitted at the fence line
39% of this site's criteria pollution
CO₂e
848 kt/yr — climate, not air quality

Who wanted it

Who asked for it
OpenAI — via a 15-year Oracle lease on the Lancium Clean Campus; developed by a Crusoe / Blue Owl / Primary Digital JV
Who approved it
Taylor County + City of Abilene tax abatements (Ch. 313/380 agreements); TCEQ air permits for ~360 MW of on-site gas turbines; ERCOT large-load interconnection
What it serves
Frontier model pre-training and inference for OpenAI
IT capacity
250 MW running of 1,200 MW announced

The flagship Stargate site: eight buildings on ~1,100 acres in the Abilene wind belt. Cooling is closed-loop, so on-site water draw is small — but roughly a third of its power comes from gas turbines permitted on the property itself.

on-site gas turbineswater-stressed basinratepayer-cost dispute

Where it is

32.3776°, -99.6672°

Water and air figures are modelled from disclosed capacity, not measured — site-level error is roughly ±40%. Diesel backup generators are not counted, so on-site figures are floors. Full method.