Hyperscale tenants on multi-hundred-megawatt leases; most names are not disclosed publicly
Who approved it
Georgia Power's 2025 IRP added roughly 10 GW of forecast data center load and new gas capacity; the Georgia PSC approved rules shifting more grid-upgrade cost onto large loads
What it serves
Wholesale colocation and hyperscale leases; Atlanta is the fastest-growing US market
IT capacity
700 MW running of 2,200 MW announced
Atlanta overtook Northern Virginia on new leasing in 2024–25. Georgia Power's load forecast tripled in three years, and the PSC's response — cost-allocation rules for large loads — has become the model other southern states cite.
ratepayer-cost disputenew gas plant built for itwater-stressed basin
Water and air figures are modelled from disclosed capacity, not measured — site-level
error is roughly ±40%. Diesel backup generators are not counted, so on-site figures are floors.
Full method.