Gigawatt Ledger · one-page briefing
Campus profile Operating
Douglas & Coweta County cluster
QTS · Microsoft · Switch · DataBank · Douglasville / Palmetto, Georgia
The resource footprint
Modelled averageIn one day, this campus consumes about
9.9650-metre swimming pools
Filled with the volume of water consumed by the campus and its electricity supply.
The actual estimate6,575,333 US gallons consumed
Power-plant water may come from a different watershed. This is a volume comparison, not a claim that households lose this water.
At current operating capacity · Annual model spread evenly over time, not a live meter. Site estimates may differ by roughly ±40%.
Comparison sizes & sources
One pool = 50 × 25 × 2 metres = 2.5 million litres (about 660,430 US gallons). Pool depths vary; this is a defined comparison size.
One home-year = 10,791 kWh, the EIA’s 2022 average US residential electricity purchases. This excludes electricity generated at home and is a fixed US benchmark for all sites.
One car-year = 4.6 tonnes CO₂, the EPA’s typical passenger vehicle tailpipe estimate. The campus model is in CO₂e; the comparison expresses approximate climate scale, not equal mixtures of pollutants.
Monthly values are annual totals ÷ 12; daily values are annual totals ÷ 365. Actual demand varies. Comparisons cover the whole campus, including non-AI uses.
Water: see the numbers and sources
This is water used up, mainly through evaporation. Power-generation water may be used in a different watershed.
- Pressure on local water
- Medium-High — a regional measure of demand compared with available water
- Where the water comes from
- Municipal potable supply
- Cooling
- Evaporative and hybrid closed-loop
- Basis
- Modelled from cooling design — WUE 0.56 L/kWh
Air: see the numbers and sources
The totals include nitrogen oxides, sulphur dioxide and fine particles. They cover both this site and the power plants supplying it.
- Health range
- $31.4–89.4 million a year. Lower bound is EASIUR national mid-range; upper is EPA benefit-per-ton at a ~$12M VSL.
- Statistical deaths
- 7.45 a year at that VSL — a national-average conversion from tons, not a local concentration study.
- Equals
- 668,618 cars of NOx
- Where it burns
- Southern Co. — Georgia / Alabama
- Generation mix
- Gas 48 · Nuclear 28 · Coal 15
- Diesel backup
- Diesel backup is not yet counted for this campus, so on-site air figures are a floor.
- CO₂e
- 1,358 kt/yr — climate, not air quality
The project, approvals and community concerns
- Who asked for it
- Hyperscale tenants on multi-hundred-megawatt leases; most names are not disclosed publicly
- Who approved it
- Georgia Power's 2025 IRP added roughly 10 GW of forecast data center load and new gas capacity; the Georgia PSC approved rules shifting more grid-upgrade cost onto large loads
- What it serves
- Wholesale colocation and hyperscale leases; Atlanta is the fastest-growing US market
- IT capacity
- 700 MW current capacity / 2,200 MW full-build scenario
Atlanta overtook Northern Virginia on new leasing in 2024–25. Georgia Power's load forecast tripled in three years, and the PSC's response — cost-allocation rules for large loads — has become the model other southern states cite.
Keep this guide handy
33.6600°, -84.7500°
Quote or share these estimates
Gigawatt Ledger (2026). Douglas & Coweta County cluster: water and air. https://gigawatt-ledger.pages.dev/site/atlantawest/. Modelled from disclosed capacity; site-level error ±40%.
Include the estimate’s date, whether it describes current or proposed capacity, and its uncertainty. Get an embeddable card.
Gigawatt Ledger · September 2026. Water and air figures are estimated from public records and disclosed capacity. How we calculate them · Use this in your community.