Campus profile Blocked or in litigation

Cerrillos

Google · Santiago (Cerrillos), Región Metropolitana, Chile

The resource footprint

Modelled average

In one day, this campus would consume about

1.1650-metre swimming pools

Filled with the volume of water consumed by the campus and its electricity supply.

The actual estimate766,902 US gallons consumed

50-metre pools · 2 metres deep
Each diagram = 1 pool. Partial shading shows the remainder.
At the campus63,909 galMaking its electricity702,994 gal

Power-plant water may come from a different watershed. This is a volume comparison, not a claim that households lose this water.

If announced plans are fully built · Not operating yet · Annual model spread evenly over time, not a live meter. Site estimates may differ by roughly ±40%.

Comparison sizes & sources

One pool = 50 × 25 × 2 metres = 2.5 million litres (about 660,430 US gallons). Pool depths vary; this is a defined comparison size.

One home-year = 10,791 kWh, the EIA’s 2022 average US residential electricity purchases. This excludes electricity generated at home and is a fixed US benchmark for all sites.

One car-year = 4.6 tonnes CO₂, the EPA’s typical passenger vehicle tailpipe estimate. The campus model is in CO₂e; the comparison expresses approximate climate scale, not equal mixtures of pollutants.

Monthly values are annual totals ÷ 12; daily values are annual totals ÷ 365. Actual demand varies. Comparisons cover the whole campus, including non-AI uses.

Water: see the numbers and sources

This is water used up, mainly through evaporation. Power-generation water may be used in a different watershed.

Total water use280M gal/yr
Evaporated on site23.3M gal
Making the power257M gal
Household comparison3,499homes, at 80,000 gal/year
Pressure on local water
Extremely High — a regional measure of demand compared with available water
Where the water comes from
Municipal potable supply
Cooling
Redesigned to air cooling after the original water-cooled permit was struck down
Basis
Modelled from cooling design — WUE 0.10 L/kWh
Air: see the numbers and sources

The totals include nitrogen oxides, sulphur dioxide and fine particles. They cover both this site and the power plants supplying it.

Nitrogen oxides159t/yr
Sulphur dioxide212t/yr
Fine particulates23.0t PM2.5
Health (EPA)$22.7M/yr
Health range
$7.94–22.7 million a year. Lower bound is EASIUR national mid-range; upper is EPA benefit-per-ton at a ~$12M VSL.
Statistical deaths
1.89 a year at that VSL — a national-average conversion from tons, not a local concentration study.
Equals
198,677 cars of NOx
Where it burns
Chile — SEN
Generation mix
Solar 22 · Coal 18 · Gas 20 · Hydro 26
Diesel backup
Diesel backup is not yet counted for this campus, so on-site air figures are a floor.
CO₂e
275 kt/yr — climate, not air quality
The project, approvals and community concerns
Who asked for it
Google — self-build
Who approved it
Chile's First Environmental Court revoked the environmental permit in January 2024, finding the groundwater assessment inadequate; Google refiled with an air-cooled design in 2025
What it serves
Google Cloud southamerica-west region
IT capacity
0 MW current capacity / 120 MW full-build scenario

The only case worldwide where a court has voided a hyperscaler's environmental permit specifically over aquifer impacts. Santiago has been in a structural drought for more than a decade, and the project became a national test of environmental review.

water-stressed basinin litigationorganised local opposition

Keep this guide handy

-33.5000°, -70.7100°

Quote or share these estimates

Gigawatt Ledger (2026). Cerrillos: water and air. https://gigawatt-ledger.pages.dev/site/cerrillos/. Modelled from disclosed capacity; site-level error ±40%.

Include the estimate’s date, whether it describes current or proposed capacity, and its uncertainty. Get an embeddable card.