Not built yet. Every figure below is what it would take and emit at the capacity its owners have announced.
Water — consumed, not returned
Taken from the basin2,875M gal/yr
Evaporated on site137M gal
Making the power2,738M gal
Basin stressExtremely High
Where the water comes from
Closed loop — negligible draw
Cooling
Air-cooled closed loop, chosen for the desert siting
Basis
Modelled from cooling design — WUE 0.06 L/kWh
Air — what the stacks emit
Nitrogen oxides1,296t/yr
Sulphur dioxide950t/yr
Fine particulates147t PM2.5
Health damages$131M/yr
Where it burns
WECC Southwest — Ariz. / N.M.
Generation mix
Gas 46 · Nuclear 22 · Solar 14 · Coal 12
CO₂e
3,213 kt/yr — climate, not air quality
Who wanted it
Who asked for it
OpenAI — via Oracle; Project Jupiter developed with Borderplex
Who approved it
Doña Ana County industrial revenue bonds approved 2025; El Paso Electric supply; New Mexico groundwater permitting under the State Engineer
What it serves
OpenAI compute under Stargate
IT capacity
0 MW running of 1,000 MW announced
Sited in the Mesilla basin, where groundwater is adjudicated and contested across the Texas–New Mexico line. The design is air-cooled specifically because water rights here are effectively unavailable.
Water and air figures are modelled from disclosed capacity, not measured — site-level
error is roughly ±40%. Diesel backup generators are not counted, so on-site figures are floors.
Full method.