Hyperion

Meta Platforms · Richland Parish, Louisiana

Water — consumed, not returned

Taken from the basin6,432M gal/yr
Evaporated on site858M gal
Making the power5,575M gal
Basin stressLow
Where the water comes from
Municipal potable supply
Cooling
Closed-loop liquid; Meta's standard water-restoration commitment
Basis
Modelled from cooling design — WUE 0.20 L/kWh

Air — what the stacks emit

Nitrogen oxides1,786t/yr
Sulphur dioxide2,273t/yr
Fine particulates260t PM2.5
Health damages$250M/yr
Where it burns
MISO South — Louisiana / Miss.
Generation mix
Gas 72 · Nuclear 14 · Coal 9
CO₂e
6,785 kt/yr — climate, not air quality

Who wanted it

Who asked for it
Meta — self-build; no external tenant
Who approved it
Louisiana Public Service Commission approved three new Entergy combined-cycle gas plants (~2.26 GW) to serve it, over intervenor objection; Richland Parish issued the local permits
What it serves
Meta Superintelligence Labs — Llama-class frontier training
IT capacity
0 MW running of 2,000 MW announced

At ~4 million sq ft it is the largest single data center under construction in the Western Hemisphere. Entergy is building three gas plants specifically for this one customer; the ratepayer-protection terms were the central fight at the LPSC.

ratepayer-cost disputenew gas plant built for it

Where it is

32.4200°, -91.5000°

Water and air figures are modelled from disclosed capacity, not measured — site-level error is roughly ±40%. Diesel backup generators are not counted, so on-site figures are floors. Full method.