Campus profile Operating

Midlothian / Red Oak

Google · Meta · Ellis County developers · Midlothian, Texas

The resource footprint

Modelled average

In one day, this campus consumes about

2.1750-metre swimming pools

Filled with the volume of water consumed by the campus and its electricity supply.

The actual estimate1,432,820 US gallons consumed

50-metre pools · 2 metres deep
Each diagram = 1 pool. Partial shading shows the remainder.
At the campus410,236 galMaking its electricity1,022,584 gal

Power-plant water may come from a different watershed. This is a volume comparison, not a claim that households lose this water.

At current operating capacity · Annual model spread evenly over time, not a live meter. Site estimates may differ by roughly ±40%.

Comparison sizes & sources

One pool = 50 × 25 × 2 metres = 2.5 million litres (about 660,430 US gallons). Pool depths vary; this is a defined comparison size.

One home-year = 10,791 kWh, the EIA’s 2022 average US residential electricity purchases. This excludes electricity generated at home and is a fixed US benchmark for all sites.

One car-year = 4.6 tonnes CO₂, the EPA’s typical passenger vehicle tailpipe estimate. The campus model is in CO₂e; the comparison expresses approximate climate scale, not equal mixtures of pollutants.

Monthly values are annual totals ÷ 12; daily values are annual totals ÷ 365. Actual demand varies. Comparisons cover the whole campus, including non-AI uses.

Water: see the numbers and sources

This is water used up, mainly through evaporation. Power-generation water may be used in a different watershed.

Total water use523M gal/yr
Evaporated on site150M gal
Making the power373M gal
Household comparison6,537homes, at 80,000 gal/year
Pressure on local water
High — a regional measure of demand compared with available water
Where the water comes from
Reclaimed / recycled water
Cooling
Mixed; reclaimed water where available
Basis
Modelled from cooling design — WUE 0.34 L/kWh
Claimed vs observed
Google Midlothian consumed 220.2 million gallons in 2025. Meta's Ellis County figure is not in Google's table; this cluster row remains modelled.
Air: see the numbers and sources

The totals include nitrogen oxides, sulphur dioxide and fine particles. They cover both this site and the power plants supplying it.

Nitrogen oxides233t/yr
Sulphur dioxide266t/yr
Fine particulates36.6t PM2.5
Health (EPA)$32.3M/yr
Health range
$11.1–32.3 million a year. Lower bound is EASIUR national mid-range; upper is EPA benefit-per-ton at a ~$12M VSL.
Statistical deaths
2.69 a year at that VSL — a national-average conversion from tons, not a local concentration study.
Equals
290,887 cars of NOx
Where it burns
ERCOT — Texas
Generation mix
Gas 40 · Wind 24 · Solar 11 · Coal 13 · Nuclear 9
Diesel backup
Diesel backup is not yet counted for this campus, so on-site air figures are a floor.
CO₂e
585 kt/yr — climate, not air quality
The project, approvals and community concerns
Who asked for it
Google and Meta, each with separate campuses in Ellis County
Who approved it
Ellis County and City of Midlothian abatements; ERCOT interconnection; Texas SB6 curtailment rules now apply to loads over 75 MW
What it serves
Google Cloud us-south1 and Meta app serving
IT capacity
300 MW current capacity / 900 MW full-build scenario

Texas SB6, passed in 2025, is the first US law letting a grid operator order data centers to disconnect during emergencies — a direct response to the winter-storm risk that ERCOT loads now represent.

water-stressed basin

Keep this guide handy

32.4820°, -96.9942°

Quote or share these estimates

Gigawatt Ledger (2026). Midlothian / Red Oak: water and air. https://gigawatt-ledger.pages.dev/site/midlothian/. Modelled from disclosed capacity; site-level error ±40%.

Include the estimate’s date, whether it describes current or proposed capacity, and its uncertainty. Get an embeddable card.