Vantage Data Centers (for OpenAI) · Port Washington, Wisconsin
Not built yet. Every figure below is what it would take and emit at the capacity its owners have announced.
Water — consumed, not returned
Taken from the basin3,476M gal/yr
Evaporated on site112M gal
Making the power3,364M gal
Basin stressLow
Where the water comes from
Closed loop — negligible draw
Cooling
Closed-loop liquid
Basis
Modelled from cooling design — WUE 0.05 L/kWh
Air — what the stacks emit
Nitrogen oxides1,613t/yr
Sulphur dioxide2,801t/yr
Fine particulates255t PM2.5
Health damages$270M/yr
Where it burns
PJM RFC — Ohio / Penn.
Generation mix
Gas 48 · Nuclear 27 · Coal 20
CO₂e
3,310 kt/yr — climate, not air quality
Who wanted it
Who asked for it
OpenAI — Vantage develops; announced as a Stargate site in 2025
Who approved it
City of Port Washington annexation and TIF; We Energies supply, with a new gas plant proposed at Oak Creek partly to serve data center load
What it serves
OpenAI compute under Stargate
IT capacity
0 MW running of 1,000 MW announced
On the Lake Michigan shore, where water is abundant but Great Lakes Compact rules govern any diversion. The binding constraint here is power, not water — We Energies has proposed new gas capacity to cover it.
Water and air figures are modelled from disclosed capacity, not measured — site-level
error is roughly ±40%. Diesel backup generators are not counted, so on-site figures are floors.
Full method.